At the end of 2010, 23 veteran experts from Wang Zhonghong and Meng Dingzhong jointly wrote a report and sent it to Beijing, directly reporting the many disadvantages of UHV: huge investment but little effect, and “three-China network” has huge risks and many hidden dangers. , The expansion of power grid scale intensifies the monopoly of the State Grid, and there are flaws in the approval procedures for exchange UHV.

This report was passed to the State Grid Corporation of China after being approved by the Premier. Coinciding with the Lunar New Year, State Grid Corporation sent a “Spring Festival greeting letter” to every elderly person. The letter did not mention the joint letter of the experts, but insisted, “The UHV communication test demonstration project is comprehensive. Successfully [4]“.

According to the plan of the State Grid, UHV should enter the acceleration orbit. However, at this time, new opposition came from Beijing. In October 2012, Zhu Rongji, who has been retired for many years, became angry: “Could it be that such a major project can also be used to cover up the sky with one hand, cut first and then play it?[5]?”

Three, the controversy deadlock, the twists and turns of the “sending power from Anhui to the East”

After Zhu Rongji made his voice, the State Grid was once again pushed to the forefront. It turned out that a number of electric power experts had written letters pointing out that all three UHV lines had the problem of unreviewed procedures. Soon, the State Council handed down an instruction of “not an example”. The “Northern Half Ring” of the East China Power Grid under construction has become the first project to go through the review process.

East China Power Grid covers the economic heart of the Jiangsu-Zhejiang-Shanghai Free Shipping Area and is also the strategic core of the State Grid’s plan. The entire six provinces and one city in East China, with less than 10% of the area, feeds one-third of the population and contributes close to 40% of the national GDP. The one responsible for reviewing this project is the China International Engineering Consulting Company, which has been responsible for the South-North Water Diversion and West-East Gas Transmission.

The State Grid originally expected that the project review would take up to one month, but I didn’t expect the application for evaluation to be handed in for one year. On October 25, 2013, the final round of the “Northern Half Ring” was finally held at the New Century Grand Hotel Beijing, and the confrontation revived.

The opposing experts still focus on two points: uneconomical and unsafe. The opinions on both sides froze and they could only vote according to the plan. As soon as the result came out-14:5, the majority was agreed. The opposing old experts also said: “19 people voted, 14