Satellite Data Map of Vulcan Mountain Hospital

Picture source: China Land Observation Satellite Data Center

In 10 days, a hospital with a capacity of 1,000 beds was officially completed. This is another “battle” that continues to race against time.

On February 2, Wuhan Vulcan Mountain Hospital was completed, with a total construction area of ​​33,900 square meters. Vulcan Mountain Hospital, with reference to the 2003 Xiaotangshan Hospital during the SARS period in 2003, officially treated patients with pneumonitis infected by a new type of coronavirus.

On the morning of the 2nd, a delivery ceremony was held in Wuhan Vulcan Mountain Hospital. Wuhan Mayor Zhou Xianwang and Deputy Commander Bai Zhongbin of the Joint Logistics Support Force signed a swap transfer document at Wuhan Vulcan Mountain Hospital, marking the official delivery of the Vulcan Mountain Hospital to the medical work of the People’s Army. By.

While another Raytheon Hospital has a total construction area of ​​75,000 square meters, there will be 1500 beds. It is expected to be delivered and put into use on the evening of February 5th, and the disease will be officially treated on February 6th.people.


China’s speed at Vulcan Mountain

Reviewing the Process of Vulcan Mountain

January 23: The task is issued

Wuhan City’s New Coronavirus Infected Pneumonia Prevention and Control Headquarters In order to strengthen the treatment of patients with new coronavirus-infected pneumonia, it was decided to build a special hospital next to the Zhidian Lake in Caidian, Wuhan, following the model of Beijing Xiaotangshan Hospital and named For Vulcan Mountain Hospital. The hospital is built with a movable board room, which can accommodate 1,000 beds, and it will be completed and put into use before February 3.

The construction land of Wuhan Vulcan Mountain Hospital is about 50,000 square meters, with a total construction area of ​​33940 square meters. The overall design is in the form of a battlefield hospital, including: consultation area, negative pressure ward building, ICU, medical technology department, network room, center. Supply warehouse, garbage disposal temporary storage room, ambulance decontamination room and other functions, with a total of 1,000 beds.

17 years ago, Xiaotangshan Hospital, which responded to the SARS epidemic, was completed within seven days. Xiaotangshan Hospital focused on treating 680 patients diagnosed with SARS and 1383 medical staff with “zero infection”, which was called “a miracle in the world’s medical history”. Today, the completion of Wuhan Vulcan Mountain and Lei Shenshan Hospital will be an important part of winning the battle against the epidemic.

There are four units participating in the construction of Vulcan Mountain Hospital, led by the China Construction Third Bureau, and three companies including Wuhan Construction Engineering, Wuhan Municipal Government, and Hanyang Municipal Government. After receiving the task on the afternoon of the 23rd, the relevant units quickly organized thousands of workers and more than 300 construction machinery and equipment to prepare for the site.

January 24: Land formation